Major Deliverables

Website:

-       Website was updated UI wise and documents were added and updated.

Project Plan:

-       Next revision was reviewed with Sponsor and changes were made afterward.

Team Schedule

-       Schedule was updated with more realistic values.

Business Requirements

-       Initial set of Business Requirements were identified and were added into BluePrint and submitted to sponsors for review.

 

Major Accomplishments

Project Plan revision, updated realistic schedule, became familiar with GWT and identified it as the avenue to pursue for ease of web-app development.

 

Concerns/Risks

-Schedule might still not be completely accurate.